Ahead of Schedule, Below Budget by up to 25%

Founded in 2000, Clevor Technologies works with contractors, engineering firms, and manufacturers on projects they execute for large companies like Potash Corp., Cameco, BHP, Areva, Mosiac and others. These customers are looking for ways to improve their productivity so that they may reduce their cost and project duration. The savings achieved depend largely on the size, complexity and the available flexibility of the project. Our customers have seen improvement in their non-material costs and the project durations of up to 25%.  For a demo, please contact us.

Picture1

 

“(A mechanical contractor for AMEC was) about six weeks behind… I introduced them to Clevor… the contract was fulfilled on time but could have been accomplished two and a half to three months sooner if they had not run into owner supplied material delays and restricted work areas.”  

  Lonnie Gieni, Senior Planner at AMEC.  Read more.

.

“Optimization at Cameco’s Cigar Lake Water Treatment Process Facilities… was instrumental in our efforts to reduce our planned duration from 12 months to 9 months.”  

  William Hughes, Senor Project Manager at Graham Construction.  Read more..


Picture1“What I saw with Clevor was very different…. work order is delivered electronically to the project every day… supervisor has the task completed, inputs the time and sends the work order back to Clevor to be uploaded into the schedule… safety instructions and QA instructions can be included in these work orders.”

   Mike Campbell, Project Manager at TESC Contracting Saskatchewan Ltd.  Read more.

Permanent link to this article: http://clevor.com/